CASE STUDY
Compressor Station
306 Reversal
Malvern Arkansas, 2019
OVERVIEW
Location
Malvern, AR
Year
2019
- Modification of four existing pig traps for bi‐directional ILI pig runs
- Installation of four (4) air to gas high pressure process gas coolers, three (3) fans each
- Installation of three (3) coalescing filter separators
- Removal of three (3) mainline existing filter separators
- Installation of new skid mounted MCC building and associated electrical power supply
- Installation of double wall, atmospheric condensate storage tank and all associated accessories
- Modifications/tie‐ins to existing ESD and Power Gas systems, including piping/valve and electrical installation
- Replacement of existing pneumatic Robert Shaw engine control panels on eight (8) units with new electronic Allen‐Bradley panels and one JS‐8 Generator control panel
- Upgrade existing Fire and Gas System
- Replacement of Station Control Plan panel with Allen‐Bradley Contol Logix system
- Installation of Remote I/O panels
- Modification of existing Shafer actuators on existing valves