CASE STUDY

Early Grove Permanent
Piping Modifications

Bristol Virginia 2020

OVERVIEW

Location

Bristol, VA

Year

2020

Services Rendered

Fabrication & Installation of permanent piping modifications for the Field and Transmissions lines (4”-8”) for the Early Grove System(s) along with (11) Anomaly Verification Digs throughout the (2) systems.

Fabrication, Removal, & Installation of a permanent launcher/receiver to existing piping to facilitate pigging. Work includes, but is not limited to, removal, concrete pier installation, barrel installation, fabrication of auxiliary piping (Kicker/equalizer/source control), pipe support installation, pressure testing, drying, painting and coating, and restoration of the construction work area. These modifications are to be performed on (4) separate lines within (2) piping systems (Field & Transmission); one is high pressure, the other is low pressure. Low Hydrogen Welding included in this Scope of Work.

    Install 4” Launcher/Receiver at MP 0.00
    Install 6” Launcher/Receiver at MP 0.00
    Install 6″ Launcher/Receiver and 4″ Mainline Valve at MP 4.27
    Install 4” Launcher at MP 6.68
    Install 8” Launcher at MP 6.68
    Install 8” Launcher/Receiver and 4” Mainline Valve at MP 7.12
    (1) High Pressure Hydrotest
    (1) Low Pressure Hydrotest
    Paint Above Ground Piping and Install Chain-link Fence at MP 7.47
    Paint Above Ground Piping and Install Chain-link Fence at MP 7.90
    Paint Above Ground Piping and Install Chain-link Fence at MP 8.53
    Paint Above Ground Piping and Install Chain-link Fence at MP 8.84
    Paint Above Ground Piping and Install Chain-link Fence at MP 9.45

Additional Scope of Work

    (11) Anomaly verification digs within the (2) systems performed concurrently with the fabrication installations.